Napoleon Avenue Bridge, Dawson Estate

Completion year 2014

Disciplines
Civil, Structural


Markets
Transport


Offices
Busselton, Perth


Key People

Dean Kelly

Civil Project Engineer

Show all

WGE arranged design and construction of a traffic bridge including coordination of specialist consultants, design co-ordination, tendering, contract administration and Superintendence of bridge and associated civil works.

This bridge forms part of the main road for the village centre of the Vasse Newtown development. The bridge spans an existing Water Corporation stormwater drain with a single span of 25m. Construction consisted of 4 precast, prestressed Tee roff beams 1.2m deep. The Precast beams were fabricated in Perth and transported to the Southwest.

Traffic volumes of 3700 vehicles per day were applicable to the Napoleon Ave bridge in Dawson Estate.