Completion year 2012
Disciplines
Electrical, Fire Engineering, Fire Protection, Hydraulics, Mechanical, Sustainability, Vertical Transportation
Markets
Health & Aged Care
Offices
Perth
Key People
Hydraulic Project Engineer, Principal
Mechanical Project Engineer, Principal
Managing Director
Fire Section Manager, Principal
Sustainability Section Manager, Principal
This project was the major enabling project for the redevelopment of the QEII Medical Centre (QEIIMC) site in Nedlands and was delivered as a two-stage managed contract by Brookfield Multiplex during 2011 and 2012.
WGE was responsible for the design and construction phase services for all the building services disciplines on this challenging project.
This $226m project is the largest of its kind in Australia and was completed within an inflexible project programme and within the confines of a fully functional hospital site - a definite challenge for all involved.
The team’s use of 3D Revit provided a significant tool for the visualization of the installation, co-ordination of the services and the ongoing operation and maintenance of the building through interfacing to the site’s facility management system.
The QEIIMC precinct accommodates a number of current buildings, including the Sir Charles Gairdner Hospital, and has future healthcare facilities planned for the site. These future plans include the relocation of a $1bn New Children’s Hospital (NCH) as well as the future relocation of the city’s Women’s Hospital. This meant that the CEP had to significantly expand to service these new facilities in addition to the existing site. The decision was made by the client that this provided the opportune time to relocate the current CEP to the rear of the site, forcing the incorporation of an extended service tunnel to connect existing infrastructure.
This intricate project was completed on time under a tight programme of work, staged to coordinate with the construction of the NCH. The existing services and CEP were operational during the construction of the new facilities necessitating meticulously planned construction, commissioning, integration and change-over phases.
Some of the particular aspects of the projects that provided the project team with significant challenges and necessitated a collaborative approach to the design and construction of the project included:
The CEP project included the following construction elements:
To an outsider viewing the high quality of the finished product with exceptional attention to detail, it would be hard to believe the rapid speed of the design and construction of this project.
More on QEII CEP:
WGE have been heavily involved in the technology side of the project. Click here to read more about our innovative technology engineering.